Koh Brothers Eco Engineering faces up to S.6 million in potential legal liabilities

Koh Brothers Eco Engineering faces up to S$57.6 million in potential legal liabilities


It reveals a binding S$20.5 million joint venture risk alongside fresh consortium, subcontractor disputes

[SINGAPORE] Catalist-listed Koh Brothers Eco Engineering on Tuesday (Aug 18) disclosed three major legal disputes exposing it to nearly S$57.6 million in potential liabilities.

This came just hours before shareholders convene to vote on moving the company to the Singapore Exchange mainboard.

The engineering and construction company flagged a maximum exposure of S$20.5 million in a joint-venture (JV) dispute, alongside a S$23.3 million consortium arbitration and a subcontractor claim of up to S$13.78 million.

The most pressing development involves the JV counterclaim.

The company said the Singapore High Court on Aug 6 dismissed applications by its subsidiary, Koh Brothers Building & Civil Engineering Contractor (KBCE), to set aside partial arbitration awards.

The JV partner then applied to the tribunal for final payment orders on Aug 7.

While Koh Brothers estimated its maximum exposure regarding these counterclaims at S$20.5 million, it noted that the JV account still holds more than S$40 million in undistributed funds.

In its first public disclosure of a separate dispute, Koh Brothers revealed that consortium partners are seeking about S$23.3 million over KBCE’s alleged failure to pay its share of capital injections. A hearing for the dispute has been postponed to an unconfirmed date.

Subcontractor sues

KBCE and Koh Keng Siang, Koh Brothers’ non-executive and non-independent chairman, are also facing a lawsuit from a former subcontractor seeking between S$9.18 million and S$13.78 million for alleged wrongful termination and conspiracy. The parties have agreed to attend a mediation session.

SEE ALSO

Koh Brothers intends to file a counterclaim against the subcontractor and stated it has not made financial provisions for the suit at this time.

Despite the legal proceedings, the company said the disputes do not cast significant doubt on its ability to continue as a going concern. It cited a net asset position of S$124.7 million as at Jun 30, and expects that the consortium and subcontractor disputes will not reach definitive conclusions within the next 12 months.

Koh Brothers Eco Engineering received in-principal approval from the bourse operator on Jul 1 to transfer its listing to the mainboard. The company previously stated that the proposed move would broaden its investor base and improve share liquidity.

In the red for H1

The group recorded a loss of S$5.7 million for the first half ended Jun 30, reversing from a S$3 million profit in H1 2025.

This was attributed to a 39 per cent increase in cost of sales stemming from higher material and procurement costs incurred by the engineering and construction division, in light of ongoing geopolitical conflicts and supply chain disruptions.

As at Jun 30, the group’s order book amounted to S$1 billion, it said on Aug 5. Cash and bank balances remained “healthy” at US$61.3 million, while shareholders’ equity was at S$114 million.

“We remain focused on disciplined project execution, operational excellence and prudent cost management for our ongoing projects,” said Koh Brothers chief executive Paul Shin.

These include the design and construction of a proposed multi-storey bus depot at Lorong Halus, piling and ground improvement-related works for a Toa Payoh integrated development, the Tuas Water Reclamation Plant and a joint venture contract for Changi Terminal 5’s intra-terminal tunnels.

In April, Koh Brothers also turned down an attempt by shareholders to force the company to distribute its stake in Oiltek, saying it is not in the best interests of the group to do so.

Shares of Koh Brothers Eco Engineering fell 2.6 per cent or S$0.003 to close at S$0.114 on Monday.



Source link

Posted in

Nathan Pine

I focus on highlighting the latest in business and entrepreneurship. I enjoy bringing fresh perspectives to the table and sharing stories that inspire growth and innovation.